AngloGold Ashanti’s Mponeng mine is located in South Africa’s Gauteng province. After the successful completion of the Pre-Feasibility study for mining below the 120 Level, the feasibility phase commenced establishing if the current hoisting capacity will be sufficient for personnel, material, slinging, and rock logistics during daily operations as well as for project-related logistics. The main objective of the simulation was to analyse how the proposed project infrastructure would tie into existing operations.
Approach
The model considered the interactions and real-world dynamic nature of:
• Shafts Logistics
• Rock Hoisting
• Level Haulage and equipment
• Personnel
• Project ramp material handling systems
These interactions were analysed to increase the shift utilisation and increase the hoisting capacity for material, by changing from a three-shift system to a two-shift system.
Results
The model simulated the complete LOM to establish if the proposed two-shift system will be sufficient to achieve the required annual target tonnages. The following graphs display whether the current hoisting capacity will be adequate to facilitate the transportation of personnel, rock, material, and slinging to reach the annual target.
For personnel logistics, the hoisting capacity was exceeded during the peak production periods.
Two shift schedule indicated sufficient capacity to hoist material cars.
Slinging did exceed the scheduled capacity during one period, but the spare capacity from the material allowed for sufficient capacity.
The study established that the proposed two-shift schedule with the current hoisting capacity will not be able to support the Hoisting operations to achieve the required production target.
Following these results, the client rescheduled the production profile to meet the hoisting capacity specified. The restated production profile is shown below.